html website templates

Sea Met Offshore Wind Measurement

Sea Met is a re-usable self-installing offshore meteorological mast and monitoring platform for water depths up to 60m that utilises a telescopic lattice and tubular mast structure fixed to a self floating concrete and steel cellular gravity base by means of a universal joint or a Lidar platform mounted at approax 30m above LAT.

Sea Met is fully built and assembled onshore, and then using a standard ocean tug the whole structure is easily deployed and commissioned offshore in a single trip lasting a matter of a few hours thus also mitigating the uncertainties of weather.

Sea Met is readily recovered and redeployed with minimal legacy impact, meaning that instead of using fixed masts that soon become redundant; a single Sea Met can be relocated several times at a fraction of the cost of a new build.

Sea Met is self-powered and will support a wide range of atmospheric, oceanographic or data acquisition instrumentation.

    A very attractive cost with re-use potential across a range fo sites

    Easily recovered and re-deployed

    Leasing options available with full data reporting service

    Full range of instrumentation to meet client's requirements

    Designed to resist wave loads and minimise vibration prviding high quality data

    Mast is specifically designed for offshore applications

    Based on proven technology used in the North Sea

    Lidar option available

    Long service life - reusable

    No legacy impact when removed

Ocean adopted a problem-led approach to firstly create a holistically designed structure from top to base specifically to overcome the fatigue and corrosion issues plaguing the meteorological masts currently employed offshore by the wind industry.  Sea Met has a design life of 25 years.

Secondly, Ocean has designed from the start on the basis that flexibility of location and the ability to easily and cheaply relocate meteorological masts is paramount to wind farm developers to ensure that they can maximise the design, density and size of any potential wind farm zone. 

Thirdly, Ocean acknowledged that Sea Met must be easily deployable and recoverable with nothing more than standard offshore tugs in order to offer wind farm developers both the flexibility of very short lead times for deployment and relocation and remove the current cost impediments of doing so. 

Utilising current budgets planned for a single mast, wind farm developers could alternatively employ multiple Sea Mets within the development zone. Sea Met also opens up the possibility of multipoint testing to either expand existing developments or to maximise the density and size of future planned sites.

Sea Met can be bespoke designed to operate in any location with water depths up to 60 metres, but to mitigate any unnecessary cost for envisaged operational requirements, two standard models are designed; Sea Met 40 to operate in water depths up to 40 metres and Sea Met 60 to operate in water depths between 40 and 60 metres. 

Both Sea Met models utilise the same design concepts and technology of a self-installing free standing Gravity Buoyant Structure (GBS) foundation mated to a tubular hull, which in turn supports a telescopic mast.


Sea Met / Sea Met Lidar
Component & Installation Overview

FOUNDATION - GRAVITY BASE AND ANCHORS



Sea Met uses a concrete and steel cellular Gravity Buoyant System (GBS) foundation.

The gravity base is a rectangular, cellular reinforced concrete structure, comprising several separate ballast compartments.

The foundation is designed to sit on the sea bed and to resist the lateral forces imposed upon it by its tower and tethers.

A steel skirt can be fitted to increase sliding resistance of the base against the sea bed. 

MAST SUPPORT

The mast is attached to the centre of the gravity base through an offshore marine quality swivel joint designed to operate over the Sea Met lifetime of 20 years under extreme saltwater corrosive environmental conditions.

The tether cables are anchored to brackets on the foundation structure and are attached to the mast via sheathed fairleads to protect from potential vessel impact.

The main section of each tether comprises multiple 6 x 19 IWRC galvanised and sheathed wire ropes. The exterior of each tether has a silicon based anti-fouling coating to reduce marine growth. 

INSTALLATION & COMMISSIONING

Sea Met is designed to be much simpler and cheaper to commission than traditional offshore masts, with over 80% of the assembly work taking place onshore. For more details, see below.


OPERATION &
MAINTENANCE

Sea Met is designed to need very little servicing and maintenance. A photovoltaic array and 600 Watt wind generators are deployed which charge a substantial battery pack, which in turn powers the data collection and transmitting equipment.

All systems on Sea Met can be monitored and interrogated from onshore allowing operators to be forewarned of any defects as soon as they start to occur. This should ensure that potential problems can be rectified prior to any full equipment failure.

In the event that some of the data gathering equipment does fail, Sea Met can be easily boarded from a boat, and the mast climbed. Equipment can either be hauled up for replacement, or if required the mast can be lowered.

In the event of substantial damage to the mast through collision etc, the gravity base will remain intact, and using a standard tug, the foundation can be re-floated and the whole structure towed back to shore for repair and refurbishment. 

TOW OUT AND INSTALLATION

Sea Met is designed to be much simpler and more economical to install and commission than traditional offshore masts, with over 80% of the assembly work taking place onshore.

Sea Met is towed out using a conventional offshore tug (STAGE 1). No specialised vessels are required for installation. A standby tug is used to escort Sea Met during the tow in case of emergency manoeuvring. This second tug is also used to expedite positional control and ballasting during installation.

Once on location, the floating Gravity Buoyant Structure (GBS) is boarded and the ballast valves which are connected through hoses to the pumps are opened. The GBS is ballasted to the seabed using seawater ballast actively pumped through the ballast valves. During the ballasted descent to the seabed the position of the Sea Met is controlled by both tugs. The location will be pre-marked and the position will be checked by DGPS.

STAGE 2 : As the GBS descends through the water column, the tower will rotate assisted by buoyancy aids and its own buoyancy until it is almost vertical. Once the GBS is settled on the sea bed in the desired position it is fully ballasted with seawater and the tower is set to the vertical. This is achieved by adjusting the pre-installed the mast tethers together with the use of deck winches on the tug.

Once locked in the vertical position the tower is safe and secure. From now on all assembly work is carried out from the work platform which is accessed via the boat landing. The temporary buoyancy is removed.

The extension of the mast sections is controlled from the work platform. The mast sections are erected using an air or hydraulic winch located on the work platform. Motive power for this is supplied from the designated work boat (probably the second tug).

The mast sections are raised (STAGE 3) using a pre-rigged cable system. The upper section is installed first followed by the next lowest section in order. As each mast section is extended from its stored position, the booms carrying the aeronautical light, anemometers and other instrumentation are attached and the equipment fitted and checked. The wind turbine power (WTG) systems and solar panels are passed over from the designated workboat using a temporary davit jib crane located on the work platform. The system is then commissioned.

Sea Met is designed to be left for long periods monitored remotely without the need for service and maintenance. Inspection is envisaged on a yearly basis. 

HEAD OFFICE
Beacon Business Park
Norman Way
Portskewett
Monmouthshire
NP26 5PY
Wales

SOUTH EAST ASIA OFFICE
15th Floor, West Block 
Wisma Selangor Dredging
142C, Jalan Ampang 
50450 Kuala Lumpur
Malaysia

LINKS


CONTACT DETAILS

Email: info@oceanresource.co.uk

Head Office Phone: +44 (0) 1291 40 80 88

Malaysia Office Phone: +60 13 439 3114

Thanks for filling out for - we will be in touch very soon!

FOLLOW US